| The
locomotive is owned by D318 Ltd., and based at the Birmingham
Railway Museum, Tyseley, Birmingham. The 16SVT
Society act as custodians of the
locomotive, and deal with fund raising from sales stands etc. Please
visit the 40118
website for the latest restoration news.
40118 was also built at the factory of Robert
Stephenson and Hawthorn in Darlington, allowing the production
capacity at Vulcan Foundry to build the 22 production Deltics. Of
the RSH batch, it was the last to be withdrawn, outliving 40124 by
over 2 years.
As with many of the class 40's, 40118 spent much
of its life out of the public gaze hauling freight trains in and
around the north and north west of England. It was none the less a
favourite with the Class 40 enthusiasts, working various passenger
trains over a long career. The loco featured in 'Robbery', the 1967
film about the 'Great' Train Robbery of 1963. With continuing
fascination about the events, 40106 and 40135 have since also been
filmed portraying the part of D326 on the ill-fated Royal Mail
Train, most notably 40106 in the hit movie 'Buster'.
After first withdrawal from BR service, the loco
was reinstated in 1985 (with 40012, 40060 and 40135) for the Crewe
remodelling work. The engine carried a new number, 97408, officially
allocated to BR Headquarters. It was withdrawn in September 1985,
only to be reinstated once more - in November 1985. It remained in
traffic until 26th February 1986 when, after 25 years and one day,
it was finally withdrawn from traffic. It was purchased on 22nd
September 1988, and moved by rail from Leicester fuel point to
Tyseley on 31st October & 1st November 1988.
Final withdrawal from BR was due to two major
faults: a seized cam-follower, causing a damaged camshaft, and a
collapsed bearing on number 5 traction motor. The motor armature had
seized, totally destroying the gear wheel on the axle. The pinion
cog on the armature was then cut off by BR to enable the engine to
remain in traffic on reduced power. Poor storage between withdrawal
and purchase also resulted in damage to the engine block. The
coolant had not been drained and this froze, punching a six-inch by
six-inch hole in the free end of the block.
Restoration work
The work undertaken so far on the engine has mostly centred on the
number 2 end, and can be detailed as follows:
Number 2 Bogie
Reunited with the engine in December 1998 after a total rebuild.
Traction motors rebuilt. Number 5 motor received a new armature from
50043 Eagle, and replacement gear case. New wheelsets fitted
(ex-40088). Brake cylinders overhauled. Bogie pipework and fittings
overhauled. Multiple working cable and fittings replaced. This bogie
has been passed fit for mainline running by Resco.
Locomotive underside
Accessible sections cleaned and overhauled. All pipework cleaned,
checked and re-lagged as appropriate. Traction motor connection
boxes restored. Fuel filling system overhauled. Water tanks removed
but not yet worked on (all internal baffle plates have rotted away).
Hand brake assembly fully overhauled. New drain holes added to
number 2 nose-end.
Number 2 Cab
Number 2 cab rebuilt. All woodwork replaced with new. Bulkhead
sheeting replaced (ex-40139). All bulkhead fittings stripped, tested
and replaced. Much of the wiring replaced. Cab heater circuits
replaced. Extra wiring circuit added for headlight, if required. All
cab gauges replaced with re-certified gauges. All power handle
equipment stripped, cleaned and refitted. Brake valve equipment
overhauled by British Rail. Windscreen wiper equipment stripped and
rebuilt. Hand brake wheel and indication flag refitted, now working.
Air System
Operating satisfactorily, leaks identified were generally minor. One
corroded brake feed pipe replaced. Several one-way valves will need
overhaul. Air receivers to be removed during 1999 for certification
and overhaul. Main reservoir tank requires extensive repairs. All
flexible pipes to be replaced.
Number 2 Nose
Bulkhead cleaned and repainted. Fixtures and fittings on the
bulkhead removed, overhauled and refitted Indicator lights and
internal lighting overhauled. Traction motor blower and exhauster
overhauled, awaiting refitting.
Power Unit
Damaged camshaft and cam-follower repaired. A-bank cleaned.
Replacement of top end parts in progress. Frost damage repaired, and
pressure tested, awaiting remedial attention. Main generator
cleaning work under way. Heaters have been placed next to the
generator for 5 years, ensuring it does not suffer from damp. Engine
room and power unit repainting in progress. Much of the fan room
bulkhead painted.
Control Cubicle and Battery Boxes
Battery boxes stripped and replaced. Wooden battery trays cleaned,
to be reused. On-board transformer and battery charging box to be
fitted with external mains socket. New batteries required. Control
cubicle half-overhauled, much wiring tested and some sections
replaced. Some relays replaced. Field diverts undergoing bench
overhaul. Control cubicle air supply to be tested. Two coats of anti
tracking paint applied to cubicle.
Boiler
Untouched so far, to be assessed when locomotive is back in traffic.
Unit is complete, and was functioning on withdrawal.
Number 1 End
Re-glazed. Air system leaks sealed by fitting gauges etc. to the cab
(gauges are not calibrated, awaiting renewal). Air supply to AWS
system sealed. Some wiring circuits replaced.
Progress update - June 2002
A round-up of recent restoration and repair work:
- · boiler roof section has now been painted
after re-skinning, awaiting refitting
- · main air reservoir corroded lower section
replaced, now ready for craning back in after re-certification
- · the first two cant rail grilles now sprayed
and ready for fitting (all being replaced due to extensive rot).
The painting of these is also being contracted out. Build
quality is superb, carried out to original construction drawings
at a very reasonable rate
- · NRN radio equipment installation is
slightly different to D345's: the main units are installed in a
purpose-built enclosure, mounted in the nose end compartment
- · all the field divert resistance banks on
top of the cubicle have been cleaned and tested
- · all three field divert contactors have now
been stripped and rebuilt. Dowding & Mills have made new
components for the divert blow out coils and new contact tips.
- · much of the cubicle wiring has been worked
on, tested and replaced as appropriate. Some wiring was found to
be different to BR schematics!
- · control cubicle cut out switch in pieces
(fortunately they know which piece goes where)
- · work on the power unit side of the cubicle
is nearing completion, while descaling and cleaning work on the
boiler side has started recently
- · no. 2 cab door frames removed and in
process of replacement (totally rotten)
- · small battery box completely refurbished
including a new battery volt meter fitted next to Battery
Isolating Switch. Large battery box requires replacement battery
shelves and repainting. Both battery boxes then require a road
crane for refitting
- · new battery charger and DC power supply
unit wired and ready to go, so 40118 can then be plugged into a
13A mains supply to operate internal lighting and battery
charging. This will be fitted in the engineroom above the
doorway to no. 2 end cab
- · all 4 turbo blowers have been disconnected
and are ready to go for overhaul (waiting on aforementioned
crane and the large battery box restoration). All four spin but
are being overhauled for good measure. A2 and B2 are to be
overhauled first. Some coolant pipe work is damaged below B2
turbo
- · flooring between no. 2 end bulkhead and the
control cubicle has been lifted, and all wiring conduits in
battery box area refurbished / replaced with new
- · no. 2 end cab is looking superb with the
work done so far. The floor panelling has been removed to expose
various conduits, pipe work and the cab door framework
- · no. 1 end bogie frames will be stripped and
grit blasted. The spare bogie, recently bought from Trevor Dean,
will be stripped and swapped for the Class 40 Appeal's spare
bogie, currently under no. 1 end. The loco can then remain
mobile, enabling the underside to be accessed for restoration
through the bogie frames, instead of being static on stands. The
overhauled traction motors and other components will then be
fitted to the restored bogie frames
- Progress update - w/e 13th, 14th July 2002
- · the air system was recharged, and the
sanders, AWS and horns were proved
- · no. 2 end bogie brake pipework was
reconnected and operated successfully for the first time in
preservation
- The startup date has been deliberately put
back so other jobs could be attended to - there is no rush to
get 40118 into traffic. The group would rather not take the loco
back out of traffic to do any of the bigger outstanding jobs;
they'd rather do them now! Several jobs can be completed when
the road crane is hired soon - as many craning jobs as possible
will be done together.
The power unit is now thought to be in good
order - the lubrication oil priming pump is thought to operate
correctly, and good water pressure is obtained. Several cylinder
heads have been removed during restoration (and stitch welding),
and nothing untoward found. So, if all goes to plan, they hope to
get the loco moving under its own power on two overhauled motors
soon. Certainly the group are itching to at least fire the unit up
in 2002.
The Future
Very early on, the group took the decision to re build the
locomotive to main line standard. This was years before any
preserved diesels ran on the main line. This does not mean that
the engine will necessarily go main line, but the work will enable
it to should the opportunities arise. Any main line work will be
on their terms - tours are more likely than Virgin trips to the
seaside, and then only once or twice a year.
Many thanks to the 16SVT
Society for providing the above
information and preservation photos.
They can be contacted via the Secretary, Colin Frew: info@40118tyseley.co.uk
Operating status: undergoing restoration - yet
to operate in preservation
Steam heat status: steam heat generator awaiting restoration
Livery: BR Corporate Blue and Yellow
Running number: 40118
© Class 40
Preservation Society
|
|